PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 08/22/07 EST. NO.02 TIME 01:05 PM R.E. NAME: YOST, RICHARD 11-289904 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 001 0011 1,452.16 E.W. @ F.A.(+) 071607 N 0011.0 0012 2,049.88 071407 N 0012.0 0013 172.50 071307 N 0013.0 0014 70.24 071707 N 0014.0 0015 152.62 071307 N 0015.0 0016 848.70 071207 N 0016.0 0016-1 -848.70 071207 N 0016.0 DAO CORRECTING ENTRY 0016-2 848.70 071207 N 0016.0 DAO CORRECTING ENTRY 0017 2,931.06 071307 N 0017.0 0018 3,955.91 071207 N 0018.0 0019 1,414.34 071207 N 0019.0 0019-1 -1,414.34 071207 N 0019.0 DAO CORRECTING ENTRY 0019-2 1,414.34 071207 N 0019.0 DAO CORRECTING ENTRY 0020 11,453.55 071207 N 0020.0 0021 20,662.56 071507 N 0021.0 0021-1 -20,662.56 071507 N 0021.0 DAO CORRECTING ENTRY 0022 4,081.59 071707 N 0022.0 0022-1 -4,081.59 071707 N 0022.0 DAO CORRECTING ENTRY 0023 994.68 072407 N 0023.0 0024 2,472.25 072107 N 0024.0 0025 4,467.57 073007 N 0025.0 0026 6,342.63 073107 N 0026.0 0027 5,538.06 073107 N 0027.0 0028 3,322.35 071207 N 0028.0 0029 7,498.92 071207 N 0029.0 55,137.42 TOTAL THIS ESTIMATE 40,178.65 TOTAL PREVIOUS ESTIMATE 95,316.07 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 08/22/07 EST. NO.02 TIME 01:05 PM R.E. NAME: YOST, RICHARD 11-289904 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- *** THERE ARE NO DEDUCTIONS FOR THIS CONTRACT *** PROGRAM CAS145 PAGE 1 DATE 08/22/07 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-289904 TIME 01:05 PM ESTIMATE NO. 02 BID OPENING 06/11/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/20/07 R.E. NAME: YOST, RICHARD DATE OF THIS ESTIMATE 08/22/07 LOCATION RERUN PROGRESS ESTIMATE 11-IMP-8-14.0 ----------------------- FCI CONSTRUCTORS, INC. IN IMPERIAL COUNTY NEAR OCOTILLO AT THE 2585 BUSINESS PARK DRIVE SOUTH FORK COYOTE WASH BRIDGE VISTA, CA 92083-8831 FED. AID NO. N O N E REBUILD BRIDGE BENT ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ 01 BOND PREMIUM LS 10,500.0000 10,500.00 0.000 0.00 PROGRAM CAS145 PAGE 2 DATE 08/22/07 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 11-289904 TIME 01:05 PM ESTIMATE NO. 02 BID OPENING 06/11/07 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 08/20/07 R.E. NAME: YOST, RICHARD DATE OF THIS ESTIMATE 08/22/07 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOUNT ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS 0.00 0.00 ADJUSTMENT OF COMPENSATION 0.00 0.00 EXTRA WORK 55,137.42 95,316.07 SUBTOTAL AMOUNT EARNED 55,137.42 95,316.07 ORIGINAL CONTRACT AMOUNT 10,500.00 TOTAL WORK COMPLETED 55,137.42 95,316.07 MATERIALS ON HAND ON SITE 0.00 MATERIALS ON HAND ELSEWHERE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 55,137.42 95,316.07 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 06/11/07 60 06/15/07 00/00/00 09/11/07 46 0 0 0 26% 77% PROGRESS IS SATISFACTORY UNSATIS PROGRESS OVERRIDEN BECAU PROGRESS IS SATISFACTORY YOST, RICHARD RESIDENT ENGINEER PROGRAM CAS145 DATE 08/22/07