PROGRAM CAS145 S C H E D U L E O F E X T R A W O R K PAGE NO. 1 DATE 10/21/19 EST. NO. 020 TIME 11:38 AM R.E. NAME: ESSAYLI,MOUSSA 12-0N2204 --------------------------------------------------------------------------- CCO REPORT REPORT TYPE OF WORK(+) WORK BR CONTR NO. NUMBER AMOUNT PERFORMED (-) DATE WK RPT.NO C O M M E N T S --------------------------------------------------------------------------- 002 0009 1,954.00 A.C. @ L.S.(+) 101519 N A9 0 004 0006 1,201.00 A.C. @ L.S.(+) 101519 N A6 0 005 0007 391.25 A.C. @ L.S.(+) 101519 N A7 0 3,546.25 TOTAL THIS ESTIMATE 499,494.91 TOTAL PREVIOUS ESTIMATE 503,041.16 TOTAL TO DATE PROGRAM CAS145 S C H E D U L E O F D E D U C T I O N S PAGE NO. 1 DATE 10/21/19 EST. NO. 020 TIME 11:38 AM R.E. NAME: ESSAYLI,MOUSSA 12-0N2204 --------------------------------------------------------------------------- DEDUCTION DESCRIPTION AMOUNT EST THIS TOTAL NO. ESTIMATE ESTIMATE --------------------------------------------------------------------------- ADMINISTRATIVE NON SUB CEM4401 CY16 -10,000.00 004 RET CEM4401 WITHOLD 10,000.00 006 0.00 0.00 LABOR COMPLIANCE VIOLATION NON SUBMIT FHWA 1391 -10,000.00 009 SUBMITTED FHWA 1391 10,000.00 010 0.00 0.00 TOTAL DEDUCTIONS 0.00 0.00 PROGRAM CAS145 PAGE 1 DATE 10/21/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 12-0N2204 TIME 11:38 AM ESTIMATE NO. 020 BID OPENING 03/17/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/19 R.E. NAME: ESSAYLI,MOUSSA DATE OF THIS ESTIMATE 10/21/19 LOCATION PROGRESS ESTIMATE 12-ORA-5-23.8/23.8 ----------------- SPINITAR IN ORANGE COUNTY 16751 KNOTT AVENUE I-5 AT SAND CANYON, D12, TMC LA MIRADA CA 90638 FED. AID NO. NHP-X059(68)E UPGRADE EXISTING AUDIO-VISUAL ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ 001 JOB SITE MANAGEMENT LS 24,579.0000 24,579.00 0.010 245.79 0.950 23,350 002 PREPARE WATER POLLUTION CONTROL PROGRAM LS 5,359.0000 5,359.00 1.000 5,359 003 TEMPORARY AUDIO VISUAL SYSTEM A1 LS 50,268.4300 50,268.43 1.000 50,268 004 AUDIO VISUAL SYSTEM (LOCATION A1) LS 240,709.5700 240,709.57 0.010 2,407.10 0.960 231,081 005 AUDIO VISUAL SYSTEM (LOCATION A2) LS 801,495.7800 801,495.78 0.020 16,029.92 0.900 721,346 006 AUDIO VISUAL SYSTEM (LOCATION A3) LS 165,166.4900 165,166.49 0.012 1,982.00 0.940 155,256 007 AUDIO VISUAL SYSTEM (LOCATION A4) LS 104,306.7100 104,306.71 0.014 1,460.29 0.930 97,005 008 AUDIO VISUAL SYSTEM (LOCATION A5) LS 105,065.5200 105,065.52 0.020 2,101.31 0.930 97,710 009 AUDIO VISUAL SYSTEM (LOCATION A6) LS 236,900.0500 236,900.05 0.010 2,369.00 0.930 220,317 010 AUDIO VISUAL SYSTEM (LOCATION B1) LS 31,270.8400 31,270.84 0.010 312.71 0.960 30,020 011 VIDEO WALL STRUCTURE LS 151,593.2400 151,593.24 1.000 151,593 PROGRAM CAS145 PAGE 2 DATE 10/21/19 STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION 12-0N2204 TIME 11:38 AM ESTIMATE NO. 020 BID OPENING 03/17/16 P R O J E C T R E C O R D - E S T I M A T E WORK PERFORMED THROUGH 10/20/19 R.E. NAME: ESSAYLI,MOUSSA DATE OF THIS ESTIMATE 10/21/19 ------------------------------------------------------------------------------------------------------------------------------------ ITEM CONTRACT ORIGINAL THIS ESTIMATE TOTAL ESTIMATE NO. ITEM DESCRIPTION UNIT PRICES AUTH. AMT QUANTITY $ AMOUNT QUANTITY $ AMOU ------------------------------------------------------------------------------------------------------------------------------------ SUBTOTAL CONTRACT ITEMS WITHOUT MOBILIZATION 26,908.12 1,783,307.84 ADJUSTMENT OF COMPENSATION 3,546.25 420,793.16 EXTRA WORK 0.00 82,248.00 SUBTOTAL AMOUNT EARNED WITHOUT MOBILIZATION 30,454.37 2,286,349.00 012 MOBILIZATION LS 1,000.0000 1,000.00 1.000 1,000 ORIGINAL CONTRACT AMOUNT 1,917,714.63 TOTAL WORK COMPLETED 30,454.37 2,287,349.00 MATERIALS ON HAND ON SITE 0.00 DEDUCTIONS 0.00 0.00 TOTAL 30,454.37 2,287,349.00 ITEMS FOR WHICH CONTRACT PRICE EXCEEDS MAXIMUM VALUE N O N E DATE CONTR CONTRACT DATE WORK BEGIN EST. DATE WORKING WEATHER NON- C.C.O. OTHER PERCENT PERCENT TIME APPROVED DAYS STARTED CONSTR COMPLETION DAYS WORKING DAYS DAYS DAYS COMPLETED ELAPSED 05/06/16 180 05/23/16 05/23/16 11/15/21 610 346 92 0 94% 100% PROGRESS IS SATISFACTORY ESSAYLI,MOUSSA RESIDENT ENGINEER PROGRAM CAS145 DATE 10/21/19