Dept. of Trans. PROGRESS Serial No. Contract No. 19-263-10-02 01-0A0404 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 5% Location: Federal Project: 01-LAK-175-25.0/27.5 HSST-P175(9) Progress payment No. 006 Payment period ending: 09-20-19 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 593,735.00 0.00 2. a. Extra Work 40,127.75 2,100.00 b. Adustment Comp. 116,700.00 0.00 3. Materials on Hand 118,969.25 4,220.33 4. Earned Subject to Retention 869,532.00 6,320.33 5. Mobilization 525,000.00 0.00 6. Total Work Completed 1,275,562.75 7. Deductions -3,000.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,391,532.00 9,320.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,320.33