Dept. of Trans. PROGRESS Serial No. Contract No. 11-263-08-31 01-0A0604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 94% 01-LAK-20-31.8/37.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-11 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 516,378.90 509,603.90 2.a. Extra Work 15,099.88 15,099.88 b. Adjustment Comp. -12,995.88 -12,995.88 3. Materials on Hand 4. Earned Subject to Retention 518,482.90 511,707.90 5. Mobilization 227,250.00 227,250.00 6. Total Work Completed 745,732.90 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 735,732.90 728,957.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 728,957.90