Dept. of Trans. PROGRESS Serial No. Contract No. 16-326-14-29 01-0A1004 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 68% Location: Federal Project: 01-DN-999 NHP-Q101(288) Progress payment No. 004 Payment period ending: 11-20-16 STEELHEAD CONSTRUCTORS INC PO BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 503,066.00 89,652.00 2. a. Extra Work 8,624.12 8,624.12 b. Adustment Comp. 3. Materials on Hand 75,684.97 75,684.97 4. Earned Subject to Retention 587,375.09 173,961.09 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 611,690.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 687,375.09 178,961.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 178,961.09