Dept. of Trans. PROGRESS Serial No. Contract No. 21-265-09-52 01-0A1204 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 87% Location: Federal Project: 01-HUM-999 NONE Progress payment No. 011 Payment period ending: 09-20-21 STEELHEAD CONSTRUCTORS JV PO BOX 536 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,388,103.20 147,681.10 2. a. Extra Work 11,608.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,399,711.20 147,681.10 5. Mobilization 200,000.00 0.00 6. Total Work Completed 1,599,711.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,599,711.20 147,681.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,681.10