Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-314-16-47 01-0A1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-128-0.0/11.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-14-11 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,026,146.10 0.00 2.a. Extra Work 90,686.30 66,844.18 b. Adjustment Comp. 8,014.06 -29,966.60 3. Materials on Hand 4. Earned Subject to Retention 2,124,846.46 36,877.58 5. Mobilization 6. Total Work Completed 2,124,846.46 7. Deductions -14,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,110,846.46 36,877.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,877.58