Dept. of Trans. PROGRESS Serial No. Contract No. 14-296-08-48 01-0A2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 77% 01-MEN-20-R0.0/R0.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-20-14 ROBERT J FRANK CONSTRUCTION INC 2806 TARMAC RD REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,618.00 3,300.00 2.a. Extra Work 34,943.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 520,561.00 3,300.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 540,561.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 540,561.00 3,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,300.00