Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-149-08-33 01-0A3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-VAR Federal Project: NONE Progress payment No. 10 Payment period ending: 03-12-13 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,120,428.50 0.00 2.a. Extra Work 30,268.88 9,029.15 b. Adjustment Comp. -16,810.00 -16,810.00 3. Materials on Hand 4. Earned Subject to Retention 1,133,887.38 -7,780.85 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,233,887.38 7. Deductions -20,000.00 8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,213,887.38 219.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219.15