Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-358-13-04 01-0A4204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-999 NONE Progress payment No. 011 Payment period ending: 12-01-15 MYERS AND SONS CONSTRUCTION LP 4600 NORTHGATE BLVD., STE 100 SACRAMENTO, CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,444,617.25 33,899.85 2. a. Extra Work 57,802.37 34,908.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,502,419.62 68,808.80 5. Mobilization 149,600.00 0.00 6. Total Work Completed 1,652,019.62 7. Deductions -11,500.00 -11,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,640,519.62 57,808.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,808.80