Dept. of Trans. PROGRESS Serial No. Contract No. 14-021-15-18 01-0A4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 45% 01-LAK-999 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-17-14 J MC LOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 810,479.72 19,244.00 2.a. Extra Work 69,759.73 1,231.24 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 880,239.45 20,475.24 5. Mobilization 100,000.00 0.00 6. Total Work Completed 980,239.45 7. Deductions 0.00 26,201.36 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 980,239.45 46,676.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,676.60