Dept. of Trans. PROGRESS Serial No. Contract No. 16-147-09-37 01-0B0004 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 82% Location: Federal Project: 01-LAK-20-13.5/31.4 STP-P020(170) Progress payment No. 015 Payment period ending: 05-20-16 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,409,417.91 -251,161.68 2. a. Extra Work 2,836,547.22 400,276.87 b. Adustment Comp. -1,486,324.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,759,640.39 149,115.19 5. Mobilization 670,000.00 0.00 6. Total Work Completed 16,429,640.39 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,404,640.39 149,115.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,115.19