Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-14-23 01-0B0004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 82% Location: Federal Project: 01-LAK-20-13.5/31.4 STP-P020(170) Progress payment No. 016 Payment period ending: 06-20-16 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,232,691.35 -176,726.56 2. a. Extra Work 3,311,156.12 474,608.90 b. Adustment Comp. -1,486,324.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,057,522.73 297,882.34 5. Mobilization 670,000.00 0.00 6. Total Work Completed 16,727,522.73 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,702,522.73 297,882.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,882.34