Dept. of Trans. PROGRESS Serial No. Contract No. 22-168-10-48 01-0B0904 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 66% Location: Federal Project: 01-DN-101-8.2/8.7 NONE Progress payment No. 023 Payment period ending: 06-20-22 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,444,149.40 544,886.13 2. a. Extra Work 646,175.28 0.00 b. Adustment Comp. 122,406.19 0.00 3. Materials on Hand 394,403.00 -82,763.00 4. Earned Subject to Retention 10,607,133.87 462,123.13 5. Mobilization 1,820,000.00 0.00 6. Total Work Completed 12,032,730.87 7. Deductions -20,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,406,633.87 462,123.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 462,123.13