Dept. of Trans. PROGRESS Serial No. Contract No. 17-206-11-25 01-0B2904 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 94% Location: Federal Project: 01-DN-101-22.9/22.9 STP-ER 19C5-004E Progress payment No. 009 Payment period ending: 07-20-17 TIMBERWORKS PO BOX 1240 MOUNT SHASTA CA 96067 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,891,337.94 349,766.44 2. a. Extra Work 39,948.99 11,790.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,931,286.93 361,556.51 5. Mobilization 285,000.00 0.00 6. Total Work Completed 2,216,286.93 7. Deductions -63,164.97 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,153,121.96 361,556.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,556.51