Dept. of Trans. PROGRESS Serial No. Contract No. 16-207-08-11 01-0B4504 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 24% Location: Federal Project: 01-HUM-299-R10.7/26.1 NH-ER 19C2-004(E) Progress payment No. 003 Payment period ending: 07-20-16 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 481,990.65 220,137.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 481,990.65 220,137.25 5. Mobilization 150,100.00 31,600.00 6. Total Work Completed 632,090.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 632,090.65 251,737.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 251,737.25