Dept. of Trans. PROGRESS Serial No. Contract No. 21-116-15-41 01-0B5004 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 95% Location: Federal Project: 01-MEN-101-3.7/5.3 NHER-19C7-0(4) Progress payment No. 049 Payment period ending: 04-20-21 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,403,567.97 19,930.00 2. a. Extra Work 2,458,303.74 149,327.75 b. Adustment Comp. 608,866.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,470,737.71 169,257.75 5. Mobilization 860,000.00 0.00 6. Total Work Completed 14,330,737.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,330,737.71 169,257.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,257.75