Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-13-40 01-0B6904 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 48% Location: Federal Project: 01-LAK-29-R41.4 NONE Progress payment No. 002 Payment period ending: 11-20-17 S.T. RHOADES CONSTRUCTION INC. PO BOX 494520 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 293,583.15 177,504.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 293,583.15 177,504.40 5. Mobilization 71,250.00 15,000.00 6. Total Work Completed 364,833.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 364,833.15 192,504.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 192,504.40