Dept. of Trans. PROGRESS Serial No. Contract No. 17-269-12-40 01-0B8204 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 29% Location: Federal Project: 01-VAR SSTG-Q101(318) Progress payment No. 002 Payment period ending: 09-20-17 APEX FENCE CO INC 19896 ALEXANDER AVENUE ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 154,567.40 115,151.70 2. a. Extra Work 3,885.25 3,885.25 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 158,452.65 119,036.95 5. Mobilization 22,500.00 22,500.00 6. Total Work Completed 180,952.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 180,952.65 141,536.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 141,536.95