Dept. of Trans. PROGRESS Serial No. Contract No. 18-114-13-50 01-0B8204 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 53% Location: Federal Project: 01-VAR SSTG-Q101(318) Progress payment No. 009 Payment period ending: 04-20-18 APEX FENCE CO INC 19896 ALEXANDER AVENUE ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 608,926.58 206,020.23 2. a. Extra Work 70,496.95 9,384.53 b. Adustment Comp. 3. Materials on Hand 139,906.43 -43,517.18 4. Earned Subject to Retention 819,329.96 171,887.58 5. Mobilization 30,000.00 1,500.00 6. Total Work Completed 709,423.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 849,329.96 173,387.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,387.58