Dept. of Trans. PROGRESS Serial No. Contract No. 12-220-15-02 01-0C2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 40% 01-DN-197-5.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-06-12 TIDEWATER CONTRACTORS, INC. 16156 HIGHWAY 101 SOUTH BROOKINGS, OR 97415 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,846.00 0.00 2.a. Extra Work 222,529.62 116,452.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 225,375.62 116,452.06 5. Mobilization 6. Total Work Completed 225,375.62 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 225,375.62 116,452.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,452.06