Dept. of Trans. PROGRESS Serial No. Contract No. 15-261-14-58 01-0C3504 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 85% Location: Federal Project: 01-LAK-29-R34.4/R40.0 NHPP-029(115) Progress payment No. 005 Payment period ending: 09-20-15 GHILOTTI BROS., INC. 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,441,665.13 687,331.71 2. a. Extra Work 38,456.30 18,345.18 b. Adustment Comp. -155,914.90 -161,914.90 3. Materials on Hand 4. Earned Subject to Retention 3,324,206.53 543,761.99 5. Mobilization 300,000.00 0.00 6. Total Work Completed 3,624,206.53 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,616,206.53 543,761.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 543,761.99