Dept. of Trans. PROGRESS Serial No. Contract No. 19-330-09-01 01-0C4704 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 63% Location: Federal Project: 01-DN-199-33.4/33.8 ACNH-P199(36) Progress payment No. 006 Payment period ending: 11-20-19 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,347,008.00 169,056.00 2. a. Extra Work 14,528.75 14,528.75 b. Adustment Comp. -155,532.00 -155,532.00 3. Materials on Hand 4. Earned Subject to Retention 1,206,004.75 28,052.75 5. Mobilization 6. Total Work Completed 1,206,004.75 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,206,004.75 29,052.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,052.75