Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-15-28 01-0C4704 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 76% Location: Federal Project: 01-DN-199-33.4/33.8 ACNH-P199(36) Progress payment No. 008 Payment period ending: 01-20-20 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,806,745.00 238,814.00 2. a. Extra Work 14,528.75 0.00 b. Adustment Comp. -155,532.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,665,741.75 238,814.00 5. Mobilization 6. Total Work Completed 1,665,741.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,665,741.75 238,814.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 238,814.00