Dept. of Trans. PROGRESS Serial No. Contract No. 14-098-15-33 01-0C6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 0% 01-LAK-20-31.6/46.5 Federal Project: NONE Progress payment No. 09 Payment period ending: 02-26-14 TEICHERT CONSTRUCTION DBA A. TEICHERT & SON, INC P.O. BOX 1890 DAVIS, CA 95617-1890 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,600.00 0.00 2.a. Extra Work 524,547.29 48,339.16 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 528,147.29 48,339.16 5. Mobilization 6. Total Work Completed 528,147.29 7. Deductions 0.00 12,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 528,147.29 60,339.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,339.16