Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-010-13-46 01-0C7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-96-R13.3/16.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-25-13 TIDEWATER CONTRACTORS INC P O BOX 1956 BROOKINGS OR 97415 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,406,254.28 -48,937.50 2.a. Extra Work 211,001.56 0.00 b. Adjustment Comp. 61,004.36 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,678,260.20 -48,937.50 5. Mobilization 296,300.00 0.00 6. Total Work Completed 1,974,560.20 7. Deductions -12,000.00 92,711.35 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,962,560.20 43,773.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,773.85