Dept. of Trans. FINAL Serial No. Contract No. 18-163-10-30 01-0C7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-101-0.7/3.0 SNHG-Q101(316) Progress payment No. 006 Payment period ending: 11-06-17 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE CT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,542,578.30 -86,800.00 2. a. Extra Work 107,554.60 36,193.87 b. Adustment Comp. 47,330.72 47,330.72 3. Materials on Hand 4. Earned Subject to Retention 1,697,463.62 -3,275.41 5. Mobilization 182,665.00 0.00 6. Total Work Completed 1,880,128.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,880,128.62 -3,275.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -3,275.41