Dept. of Trans. PROGRESS Serial No. Contract No. 13-052-08-51 01-0C7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 100% 01-HUM-96-7.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 01-20-13 6 RIVERS CONSTRUCTION, INC. P.O. BOX 1431 HOOPA, CA 95546 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 313,405.44 313,405.44 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 313,405.44 313,405.44 5. Mobilization 6. Total Work Completed 313,405.44 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 308,405.44 308,405.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 308,405.44