Dept. of Trans. PROGRESS Serial No. Contract No. 13-051-09-30 01-0C7904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 100% 01-HUM-36-21.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 02-08-13 WAHLUND CONSTRUCTION, INC. 830 HILMA DRIVE EUREKA, CA 95503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,654.00 2,654.00 2.a. Extra Work 81,643.45 81,643.45 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 84,297.45 84,297.45 5. Mobilization 6. Total Work Completed 84,297.45 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 74,297.45 74,297.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,297.45