Dept. of Trans. PROGRESS Serial No. Contract No. 20-177-14-19 01-0C8104 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 01-LAK-20-31.1/31.8 SNHG-X033(89) 01-LAK-53-7.0/7.4 Progress payment No. 014 Payment period ending: 06-20-20 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,904,873.81 639,493.71 2. a. Extra Work 526,060.64 -20,596.13 b. Adustment Comp. -50,959.16 -47,355.50 3. Materials on Hand 4. Earned Subject to Retention 5,379,975.29 571,542.08 5. Mobilization 580,000.00 0.00 6. Total Work Completed 5,959,975.29 7. Deductions -39,800.00 -34,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,920,175.29 537,542.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 537,542.08