Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-13-03 01-0C8404 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 18% Location: Federal Project: 01-HUM-101-54.3/131.8 SSTG-000C(453) Progress payment No. 003 Payment period ending: 06-20-17 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,905.00 178,470.00 2. a. Extra Work 16,175.83 16,175.83 b. Adustment Comp. -600.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 768,480.83 194,645.83 5. Mobilization 145,350.00 0.00 6. Total Work Completed 913,830.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 913,830.83 194,645.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 194,645.83