Dept. of Trans. PROGRESS Serial No. Contract No. 23-166-14-52 01-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 20% Location: Federal Project: 01-MEN-20-33.3/34.4 ACNH-P020(198) Progress payment No. 011 Payment period ending: 06-20-23 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,374,954.40 1,388,372.20 2. a. Extra Work 664,903.22 19,773.93 b. Adustment Comp. 11,617.05 0.00 3. Materials on Hand 204,647.00 0.00 4. Earned Subject to Retention 12,256,121.67 1,408,146.13 5. Mobilization 2,612,500.00 0.00 6. Total Work Completed 14,663,974.67 7. Deductions -141,724.24 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,726,897.43 1,410,146.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,410,146.13