Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-14-07 01-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 32% Location: Federal Project: 01-MEN-20-33.3/34.4 ACNH-P020(198) Progress payment No. 016 Payment period ending: 11-20-23 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,493,056.13 497,958.97 2. a. Extra Work 728,436.72 1,636.83 b. Adustment Comp. 22,015.20 13,898.15 3. Materials on Hand 94,583.00 53,366.00 4. Earned Subject to Retention 17,338,091.05 566,859.95 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 19,993,508.05 7. Deductions -149,183.42 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,938,907.63 566,859.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 566,859.95