Dept. of Trans. PROGRESS Serial No. Contract No. 24-142-12-24 01-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 33% Location: Federal Project: 01-MEN-20-33.3/34.4 ACNH-P020(198) Progress payment No. 022 Payment period ending: 05-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,075,099.76 369,248.74 2. a. Extra Work 876,277.57 1,357.96 b. Adustment Comp. 22,015.20 0.00 3. Materials on Hand 60,970.50 -33,612.50 4. Earned Subject to Retention 19,034,363.03 336,994.20 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 21,723,392.53 7. Deductions -159,183.42 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,625,179.61 330,994.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 330,994.20