Dept. of Trans. PROGRESS Serial No. Contract No. 24-240-09-12 01-0E0904 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 41% Location: Federal Project: 01-MEN-20-33.3/34.4 ACNH-P020(198) Progress payment No. 025 Payment period ending: 08-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,917,007.61 1,341,730.95 2. a. Extra Work 956,303.91 5,475.53 b. Adustment Comp. 22,015.20 0.00 3. Materials on Hand 0.00 -60,970.50 4. Earned Subject to Retention 21,895,326.72 1,286,235.98 5. Mobilization 2,750,000.00 0.00 6. Total Work Completed 24,645,326.72 7. Deductions -171,183.42 -12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,474,143.30 1,274,235.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,274,235.98