Dept. of Trans. PROGRESS Serial No. Contract No. 16-362-13-49 01-0E2004 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 39% Location: Federal Project: 01-MEN-1-43.6/70.0 ST-P001(611) Progress payment No. 003 Payment period ending: 12-20-16 BUGLER CONSTRUCTION 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 367,699.80 161,114.60 2. a. Extra Work 182,531.44 2,738.20 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 550,231.24 163,852.80 5. Mobilization 95,000.00 0.00 6. Total Work Completed 645,231.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 645,231.24 163,852.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 163,852.80