Dept. of Trans. PROGRESS Serial No. Contract No. 17-020-10-18 01-0E2004 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 56% Location: Federal Project: 01-MEN-1-43.6/70.0 ST-P001(611) Progress payment No. 004 Payment period ending: 01-20-17 BUGLER CONSTRUCTION 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 616,939.80 249,240.00 2. a. Extra Work 182,531.44 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 799,471.24 249,240.00 5. Mobilization 100,000.00 5,000.00 6. Total Work Completed 899,471.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 899,471.24 254,240.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 254,240.00