Dept. of Trans. PROGRESS Serial No. Contract No. 15-294-12-22 01-0E2104 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 52% Location: Federal Project: 01-HUM-101-11.0/103.5 NONE Progress payment No. 002 Payment period ending: 10-20-15 MYERS AND SONS CONSTRUCTION, LP 4600 NORTHGATE BLVD. SUITE 10 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,496.70 154,975.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 195,496.70 154,975.20 5. Mobilization 65,550.00 31,050.00 6. Total Work Completed 261,046.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 261,046.70 186,025.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,025.20