Dept. of Trans. PROGRESS Serial No. Contract No. 14-023-11-42 01-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 67% 01-HUM-101-15.4 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-14 VAN METER LOGGING, INC. 752B REDWOOD DR. GARBERVILLE, CA 95542 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 450,753.75 61,979.42 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 450,753.75 61,979.42 5. Mobilization 6. Total Work Completed 450,753.75 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 440,753.75 61,979.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,979.42