Dept. of Trans. PROGRESS Serial No. Contract No. 15-294-15-41 01-0E3904 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 73% Location: Federal Project: 01-VAR NONE Progress payment No. 003 Payment period ending: 10-20-15 DARREN TAYLOR CONSTRUCTION,INC 5750 PLEASANT VIEW DR. ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 740,048.17 179,271.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 740,048.17 179,271.75 5. Mobilization 6. Total Work Completed 740,048.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 740,048.17 179,271.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,271.75