Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-14-02 01-0E6404 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 29% Location: Federal Project: 01-LAK-29-34.1/R34.5 HSST-P029(132) Progress payment No. 003 Payment period ending: 06-20-18 ARGONAUT CONSTRUCTORS 360 SUTTON PLACE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 174,203.75 152,775.35 2. a. Extra Work 53,329.87 2,679.27 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 227,533.62 155,454.62 5. Mobilization 6. Total Work Completed 227,533.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 227,533.62 155,454.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,454.62