Dept. of Trans. PROGRESS Serial No. Contract No. 18-201-15-44 01-0E6404 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 76% Location: Federal Project: 01-LAK-29-34.1/R34.5 HSST-P029(132) Progress payment No. 004 Payment period ending: 07-20-18 ARGONAUT CONSTRUCTORS 360 SUTTON PLACE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 836,187.66 661,983.91 2. a. Extra Work 54,343.49 1,013.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 890,531.15 662,997.53 5. Mobilization 6. Total Work Completed 890,531.15 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 886,531.15 658,997.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 658,997.53