Dept. of Trans. PROGRESS Serial No. Contract No. 21-271-12-19 01-0E68U4 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 97% Location: Federal Project: 01-HUM-101-78.0/79.8 HSNH-Q101(361) Progress payment No. 017 Payment period ending: 09-20-21 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,402,449.76 1,188,498.10 2. a. Extra Work 102,591.47 0.00 b. Adustment Comp. -21,248.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,483,793.19 1,188,498.10 5. Mobilization 410,000.00 0.00 6. Total Work Completed 7,893,793.19 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,892,793.19 1,188,498.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,188,498.10