Dept. of Trans. PROGRESS Serial No. Contract No. 18-143-11-58 01-0E8404 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 37% Location: Federal Project: 01-HUM-283-0.1/0.1 ACST-P283(3) Progress payment No. 003 Payment period ending: 05-20-18 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 723,802.82 306,036.45 2. a. Extra Work 79,000.00 79,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 802,802.82 385,036.45 5. Mobilization 119,348.38 25,125.97 6. Total Work Completed 922,151.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 922,151.20 410,162.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 410,162.42