Dept. of Trans. PROGRESS Serial No. Contract No. 18-235-14-18 01-0E8404 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 82% Location: Federal Project: 01-HUM-283-0.1/0.1 ACST-P283(3) Progress payment No. 006 Payment period ending: 08-20-18 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,281,501.95 296,060.27 2. a. Extra Work 201,588.45 75,325.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,483,090.40 371,386.26 5. Mobilization 125,629.87 0.00 6. Total Work Completed 2,608,720.27 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,607,720.27 370,386.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 370,386.26