Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-09-34 01-0F1704 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 100% Location: Federal Project: 01-HUM-36-31.6/32.2 NONE Progress payment No. 004 Payment period ending: 08-20-15 KERNEN CONSTRUCTION P.O. BOX 1340 BLUE LAKE, CA 95525 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 395,054.51 10,428.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 395,054.51 10,428.52 5. Mobilization 6. Total Work Completed 395,054.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 395,054.51 10,428.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,428.52