Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-345-10-15 01-0F1904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-DN-199-7.5/27.4 HSNH-P199(35) Progress payment No. 004 Payment period ending: 10-02-17 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC. 2990 BAY VISTA CT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,250,830.11 0.00 2. a. Extra Work 40,963.84 0.00 b. Adustment Comp. -2,051.78 -2,051.78 3. Materials on Hand 4. Earned Subject to Retention 1,289,742.17 -2,051.78 5. Mobilization 139,210.00 0.00 6. Total Work Completed 1,428,952.17 7. Deductions 0.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,428,952.17 2,948.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,948.22