Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-13-55 01-0F3304 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 0% Location: Federal Project: 01-DN-101-12.0/15.5 NONE Progress payment No. 003 Payment period ending: 11-20-15 G R SUNDBERG, INC 5211 BOYD ROAD ARCATA, CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 168,556.59 84,275.10 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 168,556.59 84,275.10 5. Mobilization 6. Total Work Completed 168,556.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 168,556.59 84,275.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,275.10