Dept. of Trans. PROGRESS Serial No. Contract No. 17-297-15-37 01-0F4104 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 34% Location: Federal Project: 01-VAR NONE Progress payment No. 002 Payment period ending: 10-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 406,105.80 377,845.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 406,105.80 377,845.80 5. Mobilization 74,500.00 74,500.00 6. Total Work Completed 480,605.80 7. Deductions -350.24 -350.24 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 480,255.56 451,995.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 451,995.56