Dept. of Trans. PROGRESS Serial No. Contract No. 22-259-13-58 01-0F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 16% Location: Federal Project: 01-DN-199-33.5/33.9 ACNH-P199(39) Progress payment No. 003 Payment period ending: 09-20-22 STEWART ENGINEERING INC PO BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 458,666.00 103,440.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 458,666.00 103,440.00 5. Mobilization 6. Total Work Completed 458,666.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 458,666.00 103,440.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,440.00